Update 4
Feb 9th, 2012 by evergreenplanter
This week, we were preparing the final items before the build. While nothing too exciting was completed, it was mostly just “tying loose ends” to prepare ourselves for the construction phase. We estimated material quantities and costs, and then created document lists of items to be purchased for our client. We forwarded it to Helen, and with her consultation, got the approval for the materials we need. Next week we will do the build of our boxes for Evergreen. Attached is a list of our final material costs:
ok – looks good.
The cost is considerably over the funds available from the UBC-CLI (for which the client is entitled to apply). Could you check-in with her to make sure that Evergreen is willing to pay for all costs except approximately $200?
Thanks.
SN