To: Dave Michelson
From: EECE380 Team L2D8
Date: Feb 9th, 2014
Subject: Project 1 Weekly Memo 3
INTRODUCTION
This memo summarizes the status of the work that has been down this week, and also introduces the plan for the coming week.
ACHIEVEMENT FROM LAST WEEK
Our group has managed to send current voltage readings associated with exact time at the moment in proper format through emails. For the safety of messages, by using FFS commands, messages are saved to flash file memory while messages being sent to the satellite. Moreover, through ECE department, we placed our order of temperature sensors and DC motors which are necessary to the function of our project.
GOALS FOR NEXT WEEK
Firstly, we will try to finish what has not been done since previous weeks. Also, hopefully the parts we ordered will arrive next week, and we will start building up hardware part of the project.