We have completed our basic design concept after eight weeks of solid planning and meetings.
We are going to briefly discuss the latest plan and deadline we set for the completion of the project.
This is the annotated map of the latest projected plan.
The main implementations are the following:
– Changing the parking lot into two-way traffic
– Adding signs to redirect cyclists away from the parking lot
– Allowing public vehicles to stop at bus drop off zone
Expected completion dates for our poster and report:
– Week of March 4-10: rough draft of signage and plan
– Week of March 11-17: revise and complete signage plan
– Week of March 18-24: rough draft for report, get report done by March 22, copies will be send to Jeremy and Nesbit for advice
– Week of 25: finalize presentation based on report
Our progress has exceeded our expect ion, we are ahead of schedule and on pace to finish by the week of March 24.